Case Study

Two-storey extension for Southampton General Hospital

Two-storey extension for Southampton General Hospital

Garland System

R-MER CLAD

Sector

Healthcare

Garland UK returned to Southampton General Hospital to support the second phase of work, comprising a new two-storey extension and plant room at the ever-growing Oncology Ward. Utilising the existing roof space to extend upwards meant the new development would be a more cost-effective solution that was efficient on resources compared to purchasing land and building from the ground up. The much-needed extension would deliver extra beds and help address the backlog of cancer cases requiring inpatient and day-case chemotherapy.

Garland Technical Managers Paul Boole and James Hiscock worked closely with the main contractor LST Projects, building designer Kendall Kingscott and the NHS Trust Estates Team, providing technical roofing design expertise and the optimum waterproofing system specification for the hospital.

Solution

The flat roof design included a built-up waterproofing system with tapered insulation, utilising the high-performance StressPly Flex bituminous membrane system.

In conjunction with LST Projects, Garland UK approved contractor Warner Contracting began the works with a new profiled metal deck with 18mm WBP plywood installed alongside a new composite deck. A combination of EPS and PIR was installed for the new roof, varying thicknesses from 360mm-100mm to provide a gradient and tapered effect across the 1000 sqm roof areas to direct rainwater to upgraded outlets, guttering and downpipes. The upgraded insulation achieved a 0.16W/m2K U-Value rating.

The roof construction comprised a new metal and timber framework, with a self-adhesive base sheet used for the parapet upstands. A self-adhesive vapour control layer was installed on the main roof areas to mitigate the risk of hot works on site with flammable materials, particularly for the initial waterproofing phase. The new parapet wall height negates the need for any additional handrails to conform to regulations.

Once the warm roof system was in place, the existing solar PV array was reinstalled with a ballasted frame to ensure the waterproofing integrity was not compromised with penetrations to the roof system. Ballasted frames are load-supported and can be used with existing PV panels, creating flexibility for new and pre-owned systems.

The plant room comprised the R-MER CLAD system, a lightweight and hardy trapezoidal metal roof profile, including new insulation to achieve a 0.16 W/m2K U-Value.

Access walkways were laid in an alternate colour cap sheet for future maintenance. In addition, new access hatches and ladder systems, lightning conductors, cable duct flashing, and roof box housing were installed to finish the project.

Two-storey extension for Southampton General Hospital

Garland Technical Manager

Approved Contractor

  • Warner Contracting

Garland UK return to Southampton General Hospital for the second phase of roof works, to support the two-storey extension at Southampton General Hospital’s Oncology Ward.

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£900,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”

Garland UK
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.