Case Study

Sports Hall Roof R-MER CLAD Transformation

Sports Hall Roof R-MER CLAD Transformation

Garland System

R-MER CLAD

Sector

Education

The Romsey School, part of The Gateway Trust, instructed Garland UK Technical Manager Paul Boole and Technical Assistant James Hiscock to support their Condition Improvement Fund (CIF) bid application to upgrade their sports hall roof.

An essential part of the brief was ensuring the sports hall building was fully waterproof, upgrading the overall thermal efficiency, and securing a robust 20-year guarantee. The hall had long suffered from poor thermal efficiency, where most of the existing insulation had perished and slipped down the roof due to the high 42-degree pitch, resulting in little heat retention in the winter and warm air infiltration in the summer months.

The existing steel trapezoidal sheet had begun to show signs of cut-edge corrosion and general rust across the surface.  The factory-bonded coating had also started to peel away from the roof sheet, which if left untreated, the exposure would cause the metal to corrode and eventually perforate.

In conjunction with the building surveyor and The Gateway Trust, Paul Boole and James Hiscock supported the CIF bid application process from the outset, providing detailed roof condition reports, u-value calculations and core samples, sharing the range of technical design considerations to ensure the new roofing system was capable of a high-pitch installation.

Solution

R-MER CLAD, Garland’s lightweight and hard-wearing trapezoidal roofing system, was chosen for its simple installation, long lifespan and aesthetic similarity to the existing roof sheet. Lightweight enough to encapsulate the existing roof sheets, the R-MER CLAD system would include an insulated build-up to improve the thermal efficiency of the sports hall.

The 42-degree roof pitch meant safely walking on the roof was impossible, so a scaffold was erected to allow Malone Roofing to work and install the new system safely and efficiently before work commenced.

A new VCL was installed on top of the existing roof sheet before metal top hats were installed from ridge to eaves, followed by a Z profile from verge to verge. The next stage included the installation of the 280mm mineral wool insulation across the entire roof, secured within the top hat void. Combining the top hat and Z profile bar gave the sports hall roof suitable rigidity and purlin centres to support the new R-MER CLAD system and allow for wind loading requirements.

The overall roof depth had also increased with the addition of 280mm of insulation. As a result, the gutters were raised to ensure adequate water control that would efficiently remove rainwater from the roof to the ground level.

The final stage of the works saw the R-MER CLAD outer sheet installed, utilising a complimentary mix of RAL colours, including Albatross grey for the roof sheet, ridge and hip flashings, whilst Anthracite grey offset the eaves, verge and gutter details for a point of difference.

Sports Hall Roof R-MER CLAD Transformation

Garland Technical Manager

Approved Contractor

  • Malone Roofing

James Hiscock supported The Romsey School’s essential CIF bid, utilising the R-MER CLAD system to revamp the tired sports hall and overcome the poor thermal efficiency and cut-edge corrosion challenges.

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£900,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”

Garland UK
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.