Case Study

South Petherwin Primary School, Thermal Efficiency Upgrade

South Petherwin Primary School, Thermal Efficiency Upgrade

Garland System

R-MER LOC

Sector

New Build / Commercial

Over several years, multiple attempts had been made by Cornwall Council to repair the Stonewold tiles and recoat the gutter courses at South Petherwin Primary School, to stem the leaks that had continued to affect multiple classrooms across the site.

Project management surveying firm, Kendall Kingscott, appointed Technical Manager Justyn Irons, to carry out a thorough condition survey to assess the roof build-up and isolate the source of the leaks.  During the investigations, Justyn discovered that the main cause of ingress was caused by the wrong tile type being installed on the low-level pitch of the building. The gutters around the hall were too narrow and often blocked with debris, allowing ingress to flow back under the tiles into the building and directly into the classrooms below.

Solution

During the specification process, Justyn identified 3 key areas on the roof that would benefit from a unique mix of standing seam metal and bituminous membrane waterproofing systems to perfectly match the demands of the varying roof pitch gradients.

To give the best possible aesthetics for the building, Garland’s R-MER LOC metal standing seam roofing system was specified, providing a sleek architectural finish, whilst delivering optimum results against wind uplift, thermal performance, impact resistance and fire standards.

Approved Contractor Stay Dry Roofing was appointed for the works, starting with the removal of the existing tiles, battens and sarking membrane from the site. A supporting timber deck was added to the structure before laying a fully bonded bituminous VCL to the newly installed timber decking to ensure the building was fully watertight.

To improve the thermal efficiency of the building as part of the refurbishment process, a 1.6mm galvanised C-Profile was mechanically fixed to the deck across the eaves and verges prior to the installation of the insulation. The height of the C-Profile was set to match the depth of the 120mm insulation, which allowed for the face fixing of the retaining brackets, fascias and gutter inlet sheets. Through the combination of the timber deck, VCL, 120mm PIR and R-MER LOC, the insulation upgrade achieved a much improved 0.18 w/m2k, in line with current building regulations.

The aluminium R-MER LOC system comes with a high degree of prefabrication, with no mechanical folding or zipping required, making the system fast and simple to install. As well as the excellent appearance of the R-MER LOC, the choice of the system also allowed the reinstatement of the PV panels without penetrating the roof as they could be simply clamped to the seams.

On the flat sections of the roof, the StressPly Flex system included a tapered design using 120mm flat board PIR, to upgrade the thermal efficiency of the roof, whilst ensuring water can be channelled directly to drainage outlets, reducing the risk of standing water.

The Safe 2 Torch StressPly Flex system was used around the hall and any areas that couldn’t be seen from the ground, to ensure a fully bonded system could be created, with no chance of water backing up and under the tiles or the new metal system.

To improve the width of the gutter and water flow outlet points StressPly Flex was also installed onto new plywood, with renewed outlets to ensure the largest aperture possible, safeguarding the school against debris blockages in the future.

South Petherwin Primary School, Thermal Efficiency Upgrade

Garland Technical Manager

Approved Contractor

  • Stay Dry Roofing

Modern metal tile roof refurbishment at Ynystawe Primary School, with R-MER TILE ST, retaining the traditional aesthetics of the building whilst providing superior long-term durability.

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£900,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”

Garland UK
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.