Case Study

Solar & Roof Refurbishment for Multi Academy Trust

Solar & Roof Refurbishment for Multi Academy Trust

Garland System

R-MER CLAD

Sector

Education

1st Year Energy Savings

£5,840

Return on Investment

4.2 Years

As part of its wider strategic estates and asset management planning, the South Bank Multi Academy Trust wanted to install a solar PV system at Carr Junior School to reduce electricity bills and protect the site from future energy cost increases.

In the early discovery stages of the project, the Trust instructed Garland UK Technical Manager Rob Wall to conduct a roof condition survey and solar yield analysis at Carr Junior School. The detailed reports help to understand the solar project’s suitability and potential yield capabilities at the site and determine if a solar PV installation makes a suitable long-term investment.

Solution

An initial Solar Yield Analysis revealed that by installing 70 PV modules using the Solarise system, Carr Junior School would realise a 28.7 kWp system, generating 26,287 kWh a year and providing £5,840 in first-year energy savings.

The optimum solution for the roof refurbishment was an overlay, utilising the hardy yet lightweight R-MER CLAD system. The steel-profiled metal sheet cladding was designed to retrofit over the existing roof, mitigating the need to remove and replace the roof structure and sending any unnecessary waste to landfill.

Before works commenced, a structural engineer reviewed the site and confirmed the project’s viability. Rob Wall assisted the Trust with the tendering process, and Garland UK Approved Contractors, Future Roof, was appointed to carry out the quality R-MER CLAD installation works. A vapour control layer was installed, followed by 2mm galvanised steel top-hat profiles, and a bar and bracket system with adjusted bracket height, to accommodate the 150mm additional insulation. Finally, the R-MER CLAD metal profile was installed to seal and securely waterproof the site from the elements.

Once the R-MER CLAD system was in place, the Approved Installer, ERS, installed the custom Solarise system, which comprised 70 Solarwatt Classic 2.0 Photovoltaic panels at a 15° inclination across the southeast and northwest roof orientations. The lightweight Solarwatt panels deliver high energy yields, even in challenging weather conditions.

A bespoke mounting system was used to fit the unique profiles of the R-MER CLAD system. This ensured the solar panels were firmly anchored while distributing the load evenly, preventing damage to the roof sheets. A Solis inverter was chosen for its excellent conversion efficiency and robust monitoring capabilities, offering high reliability and service life for the school.

Solar & Roof Refurbishment for Multi Academy Trust

Garland Technical Manager

Approved Contractor

  • Future Roof, ERS

Technical Manager Rob Wall worked closely with the South Bank Multi Academy Trust to reduce the electricity bills at Carr Junior School and protect the site from rising energy costs in the future.

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£900,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”

Garland UK
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.