Case Study

Haslemere Rugby Club R-MER CLAD and Solarise PV System

Haslemere Rugby Club R-MER CLAD and Solarise PV System

Garland System

R-MER CLAD + Solarise

Sector

Public Sector

Size

400m2

For over 70 years, Haselmere Community Rugby Club has been the heart of the local area, catering to all age groups to play rugby in local leagues and friendly matches. The multi-use facility had become a great community asset, serving many people and clubs from formal sporting activities to informal use as an open space for events. The existing 400m2 composite panel roof at the Rugby Club pavilion had come to the end of its natural life and was no longer providing adequate waterproofing, where the kitchen and bar areas were severely affected by numerous leaks causing disruption to the everyday running of the Club.

The Local Authority instructed Garland UK Technical Manager Daniel Sandell to upgrade the existing roof to a long-term waterproofing system that would incorporate their key environmental targets to increase the building’s insulation levels and generate their own renewable energy supply.

Solution

Daniel specified Garland’s R-MER CLAD metal roof system, a lightweight and hardy trapezoidal roofing and wall system that would perfectly suit the Club’s requirements. R-MER CLAD is made from recycled materials and is 100% recyclable when it comes to the end of its natural life, making it the ideal choice to reduce the building’s overall embodied carbon.

Utilising R-MER CLAD to encapsulate the existing roof structure ensured minimal disruption to the Club’s daily activities, mitigating unnecessary landfill waste and providing a twin-skin insulated build-up to improve the building’s overall thermal efficiency.

A low-maintenance Solarise PV panel system would then be installed on top of the R-MER CLAD installation to provide a renewable energy source for the Club, reducing the building’s energy costs, lowering the operational carbon emissions and providing the opportunity to receive financial payback in the future.

Garland UK Approved Contractor, Gable Roofing, set to work on the installation incorporating a new Vapour Control Layer (VCL), followed by a galvanised steel Garland Bar & Bracket system with a bracket height of 260mm. Mineral insulation was then added to bring the roof system up to current Building Regulations, followed by Garland’s R-MER CLAD 0.7 gauge plastisol coated steel sheets. For the final details, R-MER Fix Stainless Steel Fixings with colour-matched caps and appropriate washer sizes and colour-matched Flashings were installed.

To avoid any penetrations in the new R-MER CLAD sheet being made to fix the Solarise system, Daniel specified that a custom bracket system was affixed directly onto the crowns of the R-MER CLAD roof sheet alongside EPDM washers to ensure that the roof’s waterproofing function was not compromised.

Haslemere Rugby Club R-MER CLAD and Solarise PV System

Garland Technical Manager

Approved Contractor

  • Gable Roofing

Haslemere Rugby Club were looking for a long-term waterproofing system that would also incorporate their environmental targets, to improve thermal efficiency and generate their own supply of renewable energy.

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£900,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”

Garland UK
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.