Case Study

RAAC Remediation And Roof Replacement For Academy

RAAC Remediation And Roof Replacement For Academy

Garland System

StressPly Flex

Sector

Education

Refurbishment

RAAC Remediation

Since the 1980s, the main hall at Sir Thomas Boughey Academy has remained an essential building for students and staff, hosting formal exams and assemblies throughout the year.

In response to the DfE questionnaire asking academies to review their buildings for RAAC, a Reinforced Autoclave Aerated Concrete (RAAC) deck was discovered in the main hall, resulting in the building’s immediate closure until United Endeavour Trust were able to financially fund the project to resolve the issue.

RAAC products debuted in the UK market during the 1950s and quickly gained popularity in the construction industry until the mid-1980s for their lightweight composition, fire resistance, and thermal performance. RAAC was used extensively in both commercial buildings and, particularly, in public sector buildings such as schools, colleges and hospitals.

Unfortunately, RAAC’s lightweight properties came at the cost of its structural strength. With a lifespan of just 30 years, the complete removal and replacement of a new roof deck is required to ensure the continued safety of buildings.

Solution

R-MER CLAD, Garland’s lightweight and hard-wearing trapezoidal roofing system, was chosen for its simple installation, long lifespan and In preparation for the works, a full scaffold was erected internally to create a secure working platform underneath the deck to ensure safety and efficiency during each stage of the RAAC removal. In addition, a temporary roof scaffold was installed to protect the building from any adverse weather conditions during the deck removal process.

The 800 sqm project was overseen by the main contractor, RA Edwards & Partners, and Chris Evans assigned the Garland UK Approved Contractor, Alsager Roofing, to perform the roof replacement works once the RAAC was successfully removed.

Meticulous care was taken during the removal of the RAAC deck, working in sections to ensure a smooth transition for the new joists and installing the OSB timber deck.

For the roof replacement, Chris Evans proposed the high-performance two-layer bituminous membrane system, StressPly Flex, with a tapered insulation design to improve the thermal efficiency of the building and mitigate the risk of ponding water in the future. StressPly Flex is BBA certified, fully compliant with UK building regulations and assessed for its weather tightness and service life in excess of 30 years.

The new OSB timber deck would not allow for an open flame torch-on product, so Garland’s Self-Adhesive VCL was used to encapsulate the deck, fully conforming to the NFRC’s Safe2Torch guidance. Once in place, the Garland Ultra-Vent underlay was installed, followed by the StressPly Flex cap sheet.

The final stage of the works saw the R-MER CLAD outer sheet installed, utilising a complimentary mix of RAL colours, including Albatross grey for the roof sheet, ridge and hip flashings, whilst Anthracite grey offset the eaves, verge and gutter details for a point of difference.

RAAC Remediation And Roof Replacement For Academy

Garland Technical Manager

Approved Contractor

  • Alsager Roofing

Technical Manager, Chris Evans, supports the RAAC remediation at Sir Thomas Boughey Academy and specifies the optimum system for a thermally efficient and long-lasting roof replacement…

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£900,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”

Garland UK
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.