Garland UK Technical Manager
Jordan Thomas
Approved Contractor
Bilton & Johnson Building Co, CladRight Industrial Roofing & Cladding
Garland System
R-MER CLAD
Sector
Industrial
A busy recycling centre in Coedcae Industrial Estate, Pontyclun South Wales, suffered from a crippling fire that destroyed one-third of the building leaving the rest in severe disrepair from fire damage. Garland Technical Manager, Dale Thomas, was instructed by long-term partner Cushman Wakefield to assess the extent of the damage and secure the optimum waterproofing system to get the warehouse unit returned to its former glory as a hive of activity for the local area.
Dale conducted a thorough condition survey and supplied a detailed written report to the client, highlighting the severity of the building damage and the poor condition of the existing roof sections and walls. Approximately 2,000 sqm were either damaged beyond repair or had fallen into a state of disrepair, meaning that a full refurbishment of all roof and wall sections was required before the optimum waterproofing system could be implemented.
The client did not have to use multiple suppliers on the project, thanks to Garland UK’s diverse waterproofing system offering. With high-performance metal profile, R-MER, and bituminous membrane, StressPly, systems in the range, it meant the project could continue to run smoothly and efficiently without delay.
Once all the existing roofing and cladding had been removed, work commenced on installing the new steel supports ready for the new metal R-MER CLAD system. R-MER CLAD is a profiled metal roofing and cladding system, that is both lightweight and fast to install, available in a wide range of durable, waterproof finishes. New gutters were also installed as part of the rebuild to ensure the system had the best rainwater management and was completely waterproof.
Due to the complexity of the project, Dale was on-site at least twice a week to oversee the project and ensure that all roofing and cladding works were being installed to the correct specification.
It was essential for extra measures to be taken to ensure that the green roof was protected as much as possible from the weather elements. The new-build apartments were beach facing and susceptible to strong offshore winds, so to protect the edges of the green roof system from any potential uplift, a natural solution in the form of large pebbles were hand-laid, to secure the vegetation as much as possible.