Case Study

Corfe Hills School, 3 system waterproofing scheme

Corfe Hills School, 3 system waterproofing scheme

Garland System

StressPly Flex

Sector

Education

CIF Funding Secured

£1.9M

Established in 1976, Corfe Hills School in Dorset welcomes over 800 secondary and sixth form students through their gates each year. Since achieving Academy status in 2011, Corfe Hills have been looking ahead, keen to develop a schedule of works for building improvements that support the school’s growth and ultimately safeguard the building’s future. Over time, the existing roofs across the site had experienced continuous water ingress issues that needed to be addressed. Multiple roof penetrations from the roof lights were leaking water; the existing waterproofing system and the overlaid bituminous membrane were failing in places resulting in splits and blistering, and the metal roof had rusted beyond repair. With rain seeping directly into the classrooms below, action had to be taken to ensure the site was remedied to a safe and comfortable learning environment for students and staff.

Garland Technical Manager, Paul Boole, was instructed by building surveying firm Kendall Kingscott to support Corfe Hills approaching CIF bid for the critical roof refurbishment works. An essential part of the brief was to ensure that the buildings were not only fully waterproofed but to upgrade the overall thermal efficiency, alongside securing a robust 20-year guarantee.

In support of the CIF bid, Paul carried out a thorough investigation of the school’s roof assets for Kendall Kingscott, producing core sampling data, detailed condition surveys and U-Value calculations to outline a clear specification for the works required.

Solution

Specifying a mix of StressPly FlexR-MER CLAD and Dura-Coat, the client was able to benefit from greater design choice, allowing versatility in the final specification and the best opportunity to provide the right system for Corfe Hills.

Across multiple buildings and classroom blocks, the roof was made up from a metal deck and asphalt, with a single layer of membrane that had been used as a remedial overlay 20 years ago. Avoiding the need to strip the roof and generate vast quantities of waste to landfill, it was possible for the Approved Contractor, Gable Projects, to overlay the roof with Garland’s high-performance modified bituminous membrane, StressPly Flex, in most instances.  This also included the replacement of close to 300 roof light units supplied by Whitesales Ltd.  Again careful planning was required to ensure the units were installed with minimal disruption to the classrooms beneath.

A rear block with an existing metal over clad was replaced with trapezoidal roofing and wall profile R-MER CLAD, removing a large amount of perimeter gutter courses, changing them from internal to external guttering. An R-MER CLAD reverse profile was also used on a wall section, to help solve an existing water tracking issue through the abutment wall where an extension had previously been built.

Cold applied liquid coating, Dura-Coat, was the perfect system to ensure watertight coverage in the hard to reach areas and awkward details. The Dura-Coat system installation was finished with a mineral granule, to continue the uniform aesthetic across the roof.

Corfe Hills School, 3 system waterproofing scheme

Garland Technical Manager

Approved Contractor

  • Gable Projects

Modern metal tile roof refurbishment at Ynystawe Primary School, with R-MER TILE ST, retaining the traditional aesthetics of the building whilst providing superior long-term durability.

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£900,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”

Garland UK
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.